Photo: 한국문화관광연구원(Korea Culture and Tourism Institute) · File:Suncheon Bay National Garden in South Jeolla, South Korea 04.jpg · 공공누리 제1유형(KOGL Type 1)
On November 24, the Board of Audit and Inspection (BAI), Korea's state auditor, released the results of its audit of the animation cluster project in Suncheon, South Jeolla Province. The National Assembly's Culture, Sports and Tourism Committee requested the audit on March 31 under the National Assembly Act. The project, worth 39 billion won, aims to bring animation companies together in Suncheon, and half of the money comes from the national government. The BAI found 7 cases of illegal or improper conduct, but none of its measures included disciplinary action or reprimands. Public money was spent without approval. Why did no official take responsibility?
The largest sum went into building a broadcast studio. According to the full audit report, the project plan approved by the Ministry of Culture, Sports and Tourism did not include building a new studio. It included only a remodeling of the wetland center building in Suncheon Bay National Garden for use as company space. Suncheon did not ask for approval of a new building until December 11, 2025. Then, on December 17, before receiving an answer, it signed 40 construction contracts. They totaled more than 5.5 billion won, and more than 1.235 billion won was paid out, including advance payments. The culture ministry did not approve the new building on December 24, and construction stopped on December 26.
In the same month, Suncheon bought exercise equipment, including treadmills, requested by companies moving in, worth more than 79.54 million won. The city booked it as government-supplied materials, the money the city uses to buy construction materials directly. The BAI judged that exercise equipment is not construction material. It wrote that buying the equipment without approval "in effect gave the companies preferential treatment."
Suncheon argued that it did not push the project on its own. It said its June 2025 change request described building a studio, even though it did not use the word "new building." It also said it gave a full explanation when the culture ministry inspected the site on October 22. But the BAI did not accept this argument. The studio in the June request was to be made by renovating an existing building, and the ministry approved only an extension of the project period at that time. A ministry official stated that they first heard of the plan for a new building during the October site inspection.
Bringing companies into the wetland center also violated the law. The wetland center is in a cultural park, so company offices cannot move into the building. Even so, when Suncheon changed the park plan, it skipped the committee review and the hearing of residents' opinions it was required to go through.
The five Suncheon officials in charge of these two matters were not held personally responsible. They applied for exemption from liability for proactive administration, covering both matters together. Under this system, officials are not held responsible for mistakes made while working for the public interest if there was no intent or gross negligence. The BAI's advisory committee of outside experts recommended not granting the exemption for the wetland center matter. In weighing the exemption for this matter, the BAI itself wrote that "private interests are suspected." On the use of the subsidy for other purposes, it wrote that it "is difficult to see as the result of proactive work."
Even so, the BAI granted the exemption in part and did not hold the five personally responsible. It noted that their private interests had not been confirmed. The fact that companies could not move into the park could easily have been learned by asking the Ministry of Land, Infrastructure and Transport. So the BAI judged that the real responsibility for the wetland center matter lay with the department in charge of parks rather than with the applicants. Instead, it issued an institutional caution to Suncheon and told the city to urge caution on the people involved in the parks department.
Among the measures in the audit report, this urging of caution is the only one aimed at individuals involved. The same audit also looked at the 2023 Suncheon Bay International Garden Expo. The expo organizing committee's selection of a general director for cultural events without competition also ended with an institutional caution. Personnel costs of 230 million won for the general director's team were paid as part of an 11.7 billion won event services contract.
The National Assembly asked the BAI to examine eight allegations, and three of them were closed. One of these was the allegation that the former president's wife improperly intervened to increase the budget. The 2023 budget of 200 million won was drawn up at the National Assembly's request with the government's agreement. The BAI therefore found it hard to treat this as a problem and wrote that it found no signs of intervention. However, 19.3 billion won in national funds in 2024 did not go through the Ministry of Economy and Finance's eligibility review. This review examines whether a project merits support as a subsidy program. The BAI closed this matter, saying it had already pointed out the problem in a different audit in 2024.
Whether the money paid without approval will be recovered depends on the culture ministry's measures. The BAI notified the ministry to prepare measures to cancel its decision to grant the subsidy. The ministry said it would take the necessary steps, including cancellation and an order to return the money.
How much of the more than 1.2 billion won in advance payments and the cost of the exercise equipment will the culture ministry recover? In October last year, Suncheon released 8,467 square meters of cultural park land from park status to make room for the studio. How will this land, where construction has stopped, be used? The BAI did not hold the five personally responsible, and recovering the money paid without approval is left to the culture ministry.
Sources and scope of verification
- Board of Audit and Inspection, main results of the audit of the Suncheon animation cluster project and related matters (press release, republished by Korea.kr policy briefing), November 24, 2026. Attached press release PDF, pp. 1-6.
- Board of Audit and Inspection, full public audit report on the Suncheon animation cluster project and related matters (PDF), November 2026. Table 1 (audit request items), Table 2 (summary of findings), Table 3 (handling of exemptions for proactive administration), body pp. 1-2, 4, 6-7 and 12 (reasons for closure, footnotes 29 and 30), pp. 18-23 (wetland center tenancy, exemption), pp. 24-34 (new studio and exercise equipment, opinions of related agencies, exemption), pp. 38-40 and 47-49 (peace garden, general director team exemption).
Translated from the Korean original published on November 24, 2026.
Korean original: 승인 전 스튜디오 선금 12억…순천 감사는 위법·부당 7건에 징계 없어